We’ve been busy at the build site, and we’re excited to share the progress with you!
- Site Work: Harvey Brothers brought in an excavator and skid steer to dig the footers for the home addition. L. Street Materials, Inc. assisted by hauling away the extra fill.
- Concrete Prep: Our amazing volunteers built the concrete forms and staked them in place. At the same time, the roughed in plumbing for the addition was completed.
- Inspections: The City Inspector reviewed both the plumbing and the concrete forms, and we’re thrilled to report that everything passed inspection! ✅
- Next Steps: With inspections behind us, pea stone was placed for the slab base. Harvey Brothers is now scheduling the concrete pour, which should take place within the next 2–3 weeks.
Every step brings us closer to providing a safe and stable home for a partner family. Thank you to our volunteers, sponsors, and community partners for helping make this possible!